The browser you are using is not supported by this website. All versions of Internet Explorer are no longer supported, either by us or Microsoft (read more here: https://www.microsoft.com/en-us/microsoft-365/windows/end-of-ie-support).

Please use a modern browser to fully experience our website, such as the newest versions of Edge, Chrome, Firefox or Safari etc.

Measuring change in a sector - CREDIT Case SE06

Author

Summary, in English

This case describes an ongoing initiative in Sweden with the aim of measuring the development of the Swedish infrastructure sector. The reason this case was chose is that it is one, of only a very few, national initiatives with a clear aim of taking an holistic approach to assess the development of one large share of the Swedish construction sector. The purpose of this case is to investigate:

– What measures are used

– The underlying assumptions for the choice of measure

The case study mainly contributes to WP6 (report 4)

National benchmarking (WP6) summary

In Sweden, apart from the larger Utmärkt Samhällsbyggande a more focused

program aimed at improving the competitiveness of the civil engineering

part of construction, FIA (Renewal within the civil engineering sector),

was launched in December 2003. FIA saw a need to monitor how the civil

engineering sector develops, in order to effectively plan and implement development projects.

This survey will not directly measure the effect that FIA has on the civil engineering sector. What is measured is the direction of change for the Swedish civil engineering sector during the years that FIA is active. This knowledge could indirectly be used by FIA to initiate additional studies concerning specific subjects that could guide the civil engineering sector in a desired direction.

Two main issues are of importance in regard to the CREDIT objectives.

1. The difficulty of getting in the data – although this assessment has

been initiated, approved and sponsored by the very top management of the two largest infrastructure clients and even though it is written in the procurement guidelines for both of these organisations that the survey hould be carried out jointly, between the client and the supplier consultant or contractor), it has been extremely difficult to get the survey sent in. Now, both of these two organisations have designated personnel to track down projects and make them fill it out, according to guidelines, and send it in.

2. The main performance the parties in the sector are interested to

measure and to keep track of is efficiency and productivity. They are

largely uninterested of measuring the performance of the product and/or how it affects the end-users. Similar tendencies have been seen in other national initiatives on housing in Sweden. This is to some extent in large contrast to the views and aim of the CREDIT project.

Department/s

  • Construction Management

Publishing year

2010

Language

English

Publication/Series

SBi

Document type

Report

Publisher

Danish Building Research Institute, Aalborg University

Topic

  • Construction Management

Keywords

  • enterprises
  • benchmarking
  • building
  • Measuring change

Status

Published

Report number

SBi 2010:43

ISBN/ISSN/Other

  • ISBN: 978-87-563-1456-5